- The contractor would submit a Contract Performance Report (CPR) formats 1 through 5 and an Integrated Master Schedule (IMS)
Wrong Answers:
- The contractor would submit either a Contract Performance Report (CPR) formats 1 through 5 or an Integrated Master Schedule (IMS) but not both
- The contractor would submit a Contract Performance Report (CPR) format 1 only
- The contractor would submit a Contract Performance Report (CPR) formats 1 through 5 only
- The contractor would not be required to submit any earned value related reports to the Program Management Office