The Integrated Baseline Review (IBR) assesses the validity of the performance measurement baseline (PMB) and the Integrated Master Schedule (IMS). Which of the following is NOT an IBR outcome goal?

Answer:
  • Confirming that the contractor is compliant with ISO 9000 
Wrong Answers:
  • Determining that the PMB and IMS are realistic and achievable
  • Determining that all contract work scope requirements are baselined
  • Ensuring that work scope schedules are consistent with contract delivery requirements 