The Architecture Design Technical Process has nearly been completed on the XYZ system. As a result, Derived Technical Requirements were baselined that pertain to one of the XYZ proposed subsystems, Subsystem ABC. These have resulted in the initiation of the Stakeholder Requirements Definition Process for Subsystem ABC. Meanwhile, Technical Process activities continue at the XYZ system level. This is an example of _____.

Answer:
  •  Process Recursion 
Wrong Answers:
  • Process Iteration
  • Both Process Recursion and Iteration
  • Process Incursion  