The Requirements Analysis Technical Process has been completed on a portion of the XYZ system. However, an In-Progress Review (IPR) of the work products indicated that many Technical Requirements were not adequately considered in development of the functional architecture. Consequently, a decision was made to redo Requirements Analysis using these additional missing Technical Requirements. This is an example of _____.

Answer:
  • Process Iteration
Wrong Answers:
  • Process Recursion
  • Both Process Recursion and Iteration
  • Neither Process Recursion nor Iteration