Which of the following best summarizes the Stakeholder Requirements Definition Process, one of the Systems Engineering Technical Processes?

Answer:
  • To translate stakeholder needs into technical requirements
Wrong Answers:
  • To provide traceability ultimately back to user-defined capabilities
  • To plan for, acquire, access, manage, protect, and use data of a technical nature.
  • To examine the technical risks of deviating from the program plan.